IL 68 / Dundee Road Culvert Replacement

Addressing recurring flooding and improving transportation reliability, the IL 68/Dundee Road Culvert Replacement project transformed a critical drainage crossing along a heavily traveled corridor in Northbrook, Illinois.

Location
Cook County, WI
Client
IDOT Region 1 / District 1
IMG 0954

Bloom provided planning and design engineering services for the replacement of an undersized double-barrel culvert with a new 32-foot-wide, three-sided structure carrying the Middle Fork North Branch of the Chicago River beneath the roadway.

Construction Cost
$7.5M
IMG 0964
IMG 0950

The $7.2 million project required reconstruction of the Dundee Road and Lee Road intersection, roadway approach improvements, utility relocations, retaining walls, pedestrian accommodations, and extensive stormwater and floodplain analysis.

Year Completed
2020
IMG 0949

Bloom coordinated closely with IDOT, the Village of Northbrook, utility agencies, and environmental regulators to integrate infrastructure improvements into a unified construction plan. Innovative traffic staging and temporary access strategies helped maintain local connectivity while minimizing disruptions. The resulting improvements increased drainage capacity, enhanced roadway safety, and strengthened the corridor's resilience to future flooding.