University of Wisconsin-Madison: Cogeneration Facility

Expanding the University of Wisconsin–Madison's critical energy infrastructure, the Cogeneration Facility Addition provides essential cooling capacity to support campus operations and future growth.

Location
Madison, WI
Client
State of Wisconsin, DFD/DOA
Cogeneration Facility Digital 14

Bloom provided structural engineering services for the $53.7 million project, which included a 43,500-square-foot addition housing two 5,000-ton chillers, associated mechanical systems, and rooftop cooling towers. The facility connects to the campus chilled water network through two large-diameter distribution lines.

Sq Ft
43,500
Ton Chillers
5,000
Cogeneration Facility Digital 5
Cogeneration Facility Digital 16

The structural design incorporated a robust steel framing system, reinforced concrete floors, and deep foundations extending to bedrock. Special attention was given to vibration control during construction and operation to protect sensitive equipment within the adjacent generating station and nearby research facilities. The result is a resilient, high-capacity infrastructure addition designed for long-term performance and maintainability.

Cogeneration Facility Digital 17
Cogeneration Facility Digital 13
Cogeneration Facility Digital 8
Cogeneration Facility Digital 15
Cogeneration Facility Digital 10
Cogeneration Facility Digital 18
Cogeneration Facility Digital 4
Cogeneration Facility Digital 3
Cogeneration Facility Digital 2